Grant Avenue Bridge Rehabilitation

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

 Grant Avenue Bridge

Project Overview

Grant Avenue Bridge Rehabilitation CIP Project No. 09-003: Fed Aid Project No. BHLS-5361(023)

Description

Widen and rehabilitate the existing bridge to accommodate bike lanes and sidewalks, replace substandard bridge railings, and stabilize the banks and channel of Novato Creek to minimize scouring of bridge foundations.

Location

Grant Avenue between 8th Street and Virginia Avenue

Benefit

Improve streetscape conditions and safety of pedestrians, bicyclists and motorists.

Schedule

The anticipated timeline for construction is April 2024 through January 2025. Please note that all timelines are tentative and subject to change.

Permitted work hours are 7am to 5pm, Monday - Friday

Please see the table below for information on scheduled weekend work and road closures on Grant Avenue between 8th Street & Virginia Avenue, as part of the Grant Avenue Bridge Rehabilitation Project. 

Date Additional Information 
Saturday, July 6, 2024  Weekend Work - Tentative
Wednesday, July 10, 2024  Road Closure - Grant Avenue will be closed, between 8th Street & Virginia Avenue, from 7am to 5pm while construction crews place bridge deck girders.
Monday, October 14, 2024  Road Closure - Tentative
Thursday, December 19, 2024  Road Closure - Tentative 
Monday, December 23. 2024  Road Closure - Tentative 
Friday, December 27, 2024  Road Closure - Tentative 

Grant Bridge Paving Progress
Crews completing paving work on October 14, 2024

Cost

$3,650,000 including a $3,200,000 federal Highway Bridge Program grant.

Prior Community Workshops & Meetings

Connect With Us

Sign up to receive email updates for this project. Note: select both Calendar and News categories to be notified of upcoming meeting and project updates.

Questions, comments or after-hours emergencies during construction

Minerva Construction (General Construction Contractor)
Kevin Brady
415.991.0703

On-site foreman Mike Bancroft will also be available to assist with immediate questions or concerns.

Contact

City of Novato Public Works
Gosia Woodfin, Associate Engineer
415.899.8997
gwoodfin@novato.org

Substrate, Inc. (Construction Manager)
Sunny Jhutti
415.246.4920
sunny@substrateinc.com