Construction on Arthur Street has been completed. Some minor clean up will be done by Friday, June 30. Project work will commence on Plum Street following the 4th of July Holiday, and will last for approximately 3 weeks.

*Special Note – Temporary Parking Changes on Plum Street: No Parking signs on the north side of the road may be temporarily covered and barricades may be placed on the south side of the project site for the duration of construction activities.

Project Overview

Safe Pathways to Schools Sidewalk Gap Closures - Arthur and Plum Streets; (Project # 16-010)

Description

This project includes, but is not limited to: removal and construction of sidewalk, curb & gutter, driveways, driveway approaches, ADA ramps, Type “A” catch basins, installation of prefabricated manhole, 12” HDPE storm drain, curb face drainage outlets, reconfiguration of existing sanitary sewer manholes, removal of existing AC roadway. Miscellaneous items such as construction type “A” barricade, relocation of traffic signs and replacement of pavement striping and markings will also be included.


Location

On designated routes to schools for Novato High School (on Arthur Street between Indian Valley Road and Taft Court) and for the Olive Elementary School (on Plum Street between Chase Street and the back school entrance).  

View project location on an interactive map >>


Benefit

Pedestrian and bicyclist traffic safety.


Schedule

On March 14, 2017 the City Council awarded the construction contract for this project to Coastside Concrete and Construction Inc. The first working day for this project was May 30, 2017, and the duration of the construction contract is 35 working days. Construction will begin on Arthur Street.


Cost

$440,000, including $350,000 of Marin County Measure A funds. (Strategy 4.3, Safe Pathways to Schools).


Contact Info

Project Manager
Petr Skala, Assistant Engineer
415.899.8237
pskala@novato.org

Public Works Department
415.899.8246
pw@novato.org

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer