Retaining Wall: Simmons Lane and Sunset Parkway

Print
Press Enter to show all options, press Tab go to next option

 Simmons - Before Sunset - Before 
               Simmons Lane Pre-Construction                        Sunset Parkway Retaining Wall Pre-Construction

Project Overview

Retaining Wall Replacement: Simmons Lane and Sunset Parkway (Project # 14-007)

Description

This project consists of both partial and complete demolition of a total of two existing wooden retaining walls on Simmons Lane and Sunset Parkway.


Location

Simmons Lane: Fronting 1186 and 1182 Simmons Lane.

View project location on an interactive map >>

Sunset Parkway: West side of roadway, north of San Jose Middle School.

View project location on an interactive map >>


Benefit

This project includes traffic control, water pollution control, minor earthwork, temporary and permanent sediment and erosion control measures, minor drainage improvements and final site stabilization. This project will also replace retaining walls that require extensive repairs, and will result in cost savings from reduced maintenance.


Schedule

Construction on the Simmons Lane project began on February 12, 2018, and lasted approximately two weeks. Construction on the Sunset Parkway Retaining Wall is scheduled for June 2018.


Cost

$305,000


Contact Info

Project Manager  Public Works Department 
David Dammuller, Senior Engineer  415.899.8246
415.899.8953; ddammuller@novato.org  pw@novato.org